Welding Checklist

From Fat Cat Fab Lab
Revision as of 21:02, 6 February 2022 by DHamm (talk | contribs) (Created page with "= Start up: = * ☐ Material cleaned and tungsten prepped * ☐ Shielding gas turned on (turn main tank valve counter-clockwise to open) * ☐ Regulator tank pressure (right gauge) and regulator output pressure (left gauge) is above zero - notify instructor when low * ☐ Machine plugged into 20A source, turned on (switch in back) * ☐ Fume exhaust turned on * ☐ Ground clamp secured to worktable or work * ☐ Proper attire, gloves, helmet adjusted = Shut down: = *...")
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)

Start up:

  • ☐ Material cleaned and tungsten prepped
  • ☐ Shielding gas turned on (turn main tank valve counter-clockwise to open)
  • ☐ Regulator tank pressure (right gauge) and regulator output pressure (left gauge) is above zero - notify instructor when low
  • ☐ Machine plugged into 20A source, turned on (switch in back)
  • ☐ Fume exhaust turned on
  • ☐ Ground clamp secured to worktable or work
  • ☐ Proper attire, gloves, helmet adjusted

Shut down:

  • ☐ Hot work in safe place while cooling
  • ☐ Machine off
  • ☐ Shielding gas off (turn main valve clockwise to close, leave regulator as is)
  • ☐ Clean work area
  • ☐ Fume exhaust off
  • ☐ Sharpen tungsten for next person
  • ☐ Clean electrode holder, install tungsten, coil cables, stow foot pedal
  • ☐ Return in 20 minutes for fire safety check